|
|
|
Annex
F – Environmental Appraisal Introduction
F-1 This annex summarises the key environmental issues identified in an environmental scoping exercise undertaken during 2004 by Atkins Management Consultants as an integral part of the St Helena Access Feasibility Study. More detailed environmental information is available at Sections 8 and 11, and Appendices S, T and V of Atkins’ Feasibility Study Final Report (hereafter the Atkins’ study/report). A bibliography of relevant technical reports and other publications that have informed this work is contained in Appendix S. F-2 The Atkins’ study examines the three short-listed options for access: a replacement for the current ship; a ‘medium runway’ capable of operating small business jets; and a longer runway capable of handling medium-sized aircraft such as Boeing 737-800s or equivalents. Environmental scoping has focused on the ‘long runway’ option since the impacts of the ‘medium runway’ option would be contained within that assessment. The replacement ship option would be largely neutral in environmental terms. Background
F-3
The site selected for the
construction of an airport at F-4
The ‘central basin’ of Prosperous Bay Plain – an area of about 60ha
– has, in particular, been identified as a ‘hotspot’ of invertebrate
endemicity (notably of spiders), deserving of rigorous protection and
international recognition. This has
been confirmed during ecological studies carried out in 2003/4 by F-5
The proposal to undertake such a major project at this ecologically
sensitive location has attracted considerable interest among international
conservation NGOs and individual scientists.
While it would appear that there is appreciation of the need for an
airport at F-6
As detailed elsewhere in this project memorandum, the airport will
comprise a runway 2,250m in length (orientated north/south), and terminal and
ancillary facilities, the construction of which, with associated earthworks,
will involve the disturbance of approximately 100ha of the land surface of
Prosperous Bay Plain, including approximately 15% of the area of the central
basin. In determining the optimum
runway alignment and the location of the terminal and other facilities, the
feasibility study has taken full account of the environmental factors noted
above. It has sought as far as
possible to balance the technical and regulatory criteria for the establishment
of air access at F-7
The Environmental Scoping Report (Appendix S of Atkins’ study) builds
on and updates earlier environmental screening and analysis, for example by
Cairns-Wicks in 1999 and High-Point Rendel in 2001.
It is based on a review of available literature, consultations with
relevant specialists in the Environmental
Impact Assessment (EIA) F-8
Atkins’ study has confirmed the findings of previous work that in view
of the scope, complexity and sensitivity of this major project, a full project
EIA will be required. They have
proposed that this should take the form of an integrated Environmental and
Social Impact Assessment (ESIA) and have provided outline terms-of-reference for
this at Appendix T of their final report. They
have recommended that the ESIA should be undertaken following a public
consultation and disclosure process in F-9 Atkins’ TORs required
them (among other things) to inform the preparation of draft terms-of-reference
for the environmental impact assessment at both project and strategic levels.
While to the extent possible Atkins have scoped some of the off-site,
indirect, potential impacts associated with tourism development, they have
concluded (and DFID and SHG have accepted) that a strategic environmental
assessment would not be appropriate in the absence of any specific current
policy initiative on which it could be based. Environmental legislation, assessment procedures and
institutional issues
F-11
The SHG’s human resource capacity in the field of environmental
management and regulation is currently insufficient to handle a project of this
magnitude, complexity and sensitivity. Nor
is it necessarily optimally placed within the government system to be able to
discharge its responsibilities effectively.
The consultants have therefore proposed that the SHG should consider
establishing an expanded and independent environment agency (or similar) with
responsibility for all environmental regulatory and management functions
including, initially, oversight of all environmental aspects of the airport
project and associated developments. F-12 Atkins have recommended that this agency should be supported by externally sourced specialist environmental technical assistance. This could be on a part-time basis initially, but would need to become full-time for the duration of the construction phase of the airport when an Environmental Regulator, with adequate delegated authority, will be required. The Environmental Regulator will be recruited by SHG/DFID and will report directly to the Project Management Unit. A local counterpart environmental technician (if available) would also be appointed to provide specialist support and continuity into the operational phase of the project. Financial provision for this technical assistance is included in overall project costs. Impact
scoping of the airport site
F-13 The main potential impacts of airport construction are on the Prosperous Bay Plain ecosystem and specifically on landscape, with just under 100ha affected by the construction (including the filling of Dry Gut) and on the globally important endemic invertebrate community in the Central Basin of the Plain as noted in F-4 above. F-14 While the impact on the landscape and invertebrates will be significant, it is expected that through careful design, construction and subsequent restoration, the effects can be substantially mitigated. The interim findings of the ecological research on invertebrates referred to above has already influenced the proposed location and alignment of the runway during outline design. It could be argued that the engineering achievement of the runway, whose colours will largely blend into the landscape, may more than mitigate other visual loss. But as this is the only feasible site for an airport on the island, some change in the landscape will inevitably have to be tolerated. The visual impact of the substantial embankment in Dry Gut will be limited, other than when viewed from the seaward direction. F-15 In addition to the major landscape impacts, the scoping study has identified and provided preliminary observations on a range of other potential environmental impacts and issues, many of which will require more detailed attention in the ESIA. These include impacts on flora, fauna (invertebrates, the Wirebird and other birds) and such issues as meteorological data, acquisition of construction materials, noise, air quality, fuel storage, drainage, water supply, solid and hazardous waste management, power supplies, navigation systems, emergency procedures, construction camp, and health and safety. Impact
scoping of haul and operational access routes
F-16
It is considered likely that the
development of access routes to the airport site, both for construction and
operational purposes, could potentially have at least as great an environmental
impact as the construction of the airport itself. The
ESIA will therefore pay particular attention to these. F-17
Three options for haul routes were examined in detail.
The one via Turks Cap was eliminated because of rock fall risks and poor
landing potential. The route from F-18
Five potential operational routes, all of approximately a similar
distance from the air terminal to Impact
scoping of tourism development
F-19
The environmental impact of tourism development is expected to be minimal
while tourist numbers remain below 200/day.
As numbers increase to 200-500/day, impacts may occur on some marine
activities (such as dolphin watching) and in some wilderness walking areas (such
as the central peaks) in which case some level of control may be required.
Above 500/day, impacts would increase significantly both on the natural
environment and on use of utilities. The
consultants have recommended that carrying capacity assessments should form an
important part of the ESIA. Environmental
impact assessment process and public consultation
F-20 Atkins have proposed that the key stages of the ESIA process should be as follows: · Finalise draft ESIA TORs · Develop public consultation and disclosure plan · Develop project description and distribute to stakeholders together with TORs · Hold public meetings to receive stakeholder feedback on the TORs · Finalise ESIA TORs · Undertake ESIA simultaneously with design stage · Develop mitigation strategy and environmental management plan · Consult with stakeholders on draft ESIA report · Finalise ESIA · Implement environment management plan F-21 The public consultation and disclosure process is important both for reasons of transparency and information dissemination, and so that there can be the widest possible input by interested and affected parties, with a view to achieving consensus on desired outcomes, promoting ownership of the process, and reducing the potential for misunderstandings and conflict. Environmental
management plan, mitigation and monitoring
F-22 The objective of the environmental management plan (EMP), which would be developed during the ESIA and constitute its main output, would be to provide a framework for the implementation of the ESIA recommendations for best practice in environmental management and of the mitigatory actions proposed. The EMP would address such matters as: environmental management policies and systems (to include a pollutant spill contingency plan); health and safety management plan; waste management plan; training plan; traffic management plan; mitigation and restoration policies, plans and procedures; monitoring activities; and a plan for integrating implementation of the EMP with the overall project development plan. Relevant elements of the EMP, which will be developed in conjunction with the final design process, will be carried forward into construction as contractual obligations. F-23 Atkins’ study has identified outline mitigation strategies and cost estimates for these. For example, key strategies will be developed for land reinstatement programmes for the airport environs and access routes, with the objective of creating environmental conditions favouring recolonisation by invertebrates and endemic plants. Other mitigatory activities will be dependent on the choice of access routes; for example further investigations on Wirebird ecology and the creation of additional habitat may be required if the Rupert’s haul/operational route is selected. F-24 Throughout the construction process compliance monitoring of the EMP will be the responsibility of a full-time Environmental Regulator, assisted by a local counterpart ecologist, both of whose costs will be met through the project. Costs F-25
The cost of undertaking further environmental work associated with
the development of the ‘long-runway option’ for air access is estimated to
amount to a total of █████.
At less than 1% of the total estimated project cost this falls within the
norm for a project of this nature. Of
this, the environmental and social impact assessment would account for
█████; the mitigation costs (including further
ecological studies) █████; and institutional
support costs █████. |
Copyright © 2005 ST HELENA NEWS MEDIA SERVICES |